Earned value management for dummies: What you need to know (2024)

The definition of earned value management for dummies

In simple terms, earned value management (EVM) is a project management technique which enables someone to measure the amount of earned value which has been produced on a project to date.

The definition of earned value management for dummies is that EVM is a way to measure project performance on the basis of:

  • Time - Comparing the amount of work which has been done compared to what was scheduled (are we going to deliver in time?)
  • Cost - Comparing the amount we have spent to the original project budget (have we spent more or less than we had planned)

Many of the methods for project management tracking are one dimensional in that they only assess performance based on cost alone or schedule alone, but earned value enables a project manager or assessor to look at the project and factor in multiple facets of performance.

Earned value management is one of the most powerful tools in the project management arsenal, which is why we have broken down this measure and examples in the rest of this earned value management for dummies article.

Who uses EV?

Earned value management can be used on almost any project, but it is most common in industries like construction and mining, where projects span over long periods of time, involve long forecasts and projects and many moving parts.

On some mega construction projects, the initial budget at completion (planned expenditures) are in the billions, and the project has a schedule of more than 5 years.

Relying on initial forecasts and projections from the planning phase of these projects throughout the project would not be smart. Projects like these suffer from the influences of many different internal and external shocks including changing commodity prices, weather, personnel changes, political changes, technology changes and more. The longer the project, the more likely there will be major shifts which effect the project.

To mitigate the chances that these changes will blow the budget or schedule way out of whack or leave a client, contractor or subcontractor in trouble, companies need to assess their performance throughout a project.

They need to understand early on in the project how different teams and parties are performing so they have the information they need to make smart and informed decisions about what to do to get the project back on track.

Earned value management for dummies is applicable to many different workers and many different industries.

Earned value management calculation for dummies

The most useful part of this earned value management for dummies article is probably going to be this section, which provides you with an example of an earned value calculation.

One of the major benefits of EVM is that it is an objective and quantitative measure. A project manager can't rely on their gut instinct or the advice of a friendly contractor or subcontractor. The earned value formula and EVM metrics force project managers to look at performance objectively.

As an example of what a typical earned value calculation might look like, let's take this example:

An infrastructure project to build a 100km piece of road is scheduled to be completed in 12 months, and the initial budget for the project is $10,000,000.

After 3 months, the project manager wants to see how the project is performing. She looks at current progress and finds that 25% of the project has been completed (20km of road has been finished) and $2,700,000 has been spent.

From these numbers, we can begin to formulate our earned value measures.

First, we know that our budget at completion (initial budget) = $10,000,000

Second, because we are 3 months through our 12 month project (25%), we also know that our planned value (PV) at this stage of the project was = $2,500,000 (25% x our budget of $10,000,000)

Now that we have these numbers, we can produce our key earned value management calculations.

First, we want to find our earned value on the project so far so we:

Earned value = % of project complete x BAC = 25% x $10,000,000 = $2,500,000

On face value, this looks good, our earned value is equal to our planned value, which means we are on schedule.

But, given that earned value is multi-dimensional, we also need to compare the project from a cost basis. From the above paragraph, we can see we have spent $2,700,000 to date.

We can place this number in our cost variance calculation to see how we are performing on a cost basis:

Cost variance = Earned value - actual cost = $2,500,000 - $2,700,000 = -$200,000

Like most negative numbers or numbers in the 'red', this is not a good thing. Because the cost variance result is negative, we are over budget, and we are over budget by $200,000.

This is really helpful information, because now we understand that to stay on schedule, we have spent $200,000 extra dollars. To stay on schedule during the next 9 months and bring the project back onto budget, we are going to have to find some new efficiencies or reduce costs somewhere.

If the project manager had just seen that the project was on schedule, they may have continued as planned and only realised they were ~$800,000 over budget at the end of the project.

You can learn more about all of the earned value formulas here.

How do people track EVM?

The great thing about this earned value management for dummies article is that it summarises the theoretical aspects of earned value really well (and this is the purpose of most 'for dummies' reading).

But given that earned value is a project management technique, and projects are very tangible, it's also helpful to understand what tracking and using earned value management on a real project looks like.

While there is of course some variation in what different projects in different industries look like, most of them require the same core ingredients:

  • People plan the project and the schedule
  • People document progress once the project begins
  • People reconcile all of this data into a way that makes it possible to compare progress to the plan (through earned value or some other metrics)

To do all of this work, companies employ different methods.

Some companies still have heavily manually methods for documenting, tracking and computing all of this data. These methods involve capturing information using paper, word docs and PDFs on site - and then reconciling that data into spreadsheets where project manager can build formulas and graphs.

Other companies choose to digitise and streamline these processes through project management softwares and tools like Dashpivot.

The rise of cloud-based solutions and enterprise content management softwares has enables these companies to better manage all of the data being collected on site.

Workers can document progress using phones and tablets on sites, and the systems take care of all of the data movement so that all of that information is organised and available in real-time.

Project managers can then display this information and easily calculate earned value management and other important project measures across safety, quality and more.

Many project managers are 'stuck' doing earned value management in the manual and time-consuming methods of the past, but people reading this earned value management for dummies article can easily start doing earned value using the smarter methods of today.

Earned value is a critical project measure, but measuring and analysing these metrics shouldn't take away from making progress on a project and doing value-added work, which it can when the admin and work associated with simply getting information from the site to the office requires the majority of a supervisor, engineer or IT persons time.

Earned value management for dummies: What you need to know (2024)

FAQs

What is earned value management in simple words? ›

Earned value management (EVM) is a project management methodology that integrates schedule, costs, and scope to measure project performance. Based on planned and actual values, EVM predicts the future and enables project managers to adjust accordingly.

What is earned value for dummies? ›

The definition of earned value management for dummies is that EVM is a way to measure project performance on the basis of: Time - Comparing the amount of work which has been done compared to what was scheduled (are we going to deliver in time?)

What is the basic EVM? ›

Essentially, EVM measures project performance against the baselines outlined in your project scope management plan. Using your original goals as benchmarks, you can measure progress more accurately and draw actionable conclusions.

What is an EVM example? ›

Earned value management example – 1. Let's imagine we are building a wind power plant. The project is set to be completed in 10 months with an estimated cost of $500,000. The project has been running for 5 months now, the team has spent $220,000 and completed an amount of work worth $255,000.

What is the 50 50 rule earned value? ›

It assignes 50% of a project's value at the start of the project and delivers the rest at the project's completion. By examining the progress of their initial project phases, they can keep their projects and their spending focused. Earned value is one of three important data points for projects.

What are the 3 earned value methods? ›

EVM Budget summary matrix

This determination begins with classifying work tasks as one of three types: discrete, apportioned effort, or level of effort (LOE).

What are the principles of EVM? ›

EVM Principles. At its essence, Earned Value is a measure of project performance comparing work completed against work planned, as of a given date. It is used to (1) measure, (2) forecast, and (3) improve project performance for an organization.

How to read EVM? ›

SPI = (EV) / (PV)

A value greater than 1 is typically good (it indicates your are ahead of schedule vs. plan) and a value less than 1 is typically bad (it indicates you are behind schedule vs. plan). A value of 1 indicate you are on plan.

What are the three basic metrics of Earned Value Management? ›

The Essential EVM Metrics You Need to Track

Here are the key metrics you need to focus on: Planned Value (PV): The budgeted cost of the work scheduled to be completed. Earned Value (EV): The value of the work actually completed. Actual Cost (AC): The actual cost incurred for the completed work.

What is the formula for Earned Value Management? ›

Earned value management formulas
Formula NameFormula
Schedule Performance IndexSPI = EV / PV
Estimate At CompletionEAC = BAC / CPI
Estimate To CompletionETC = EAC – AC
To-Complete Performance Index (BAC)TCPI = (BAC-EV) / (BAC-AC)
7 more rows

Is Earned Value Management hard? ›

However, given the constraints of operating within the restrictions and limitations of a government agency, EVM can be very difficult and in some situations impossible to attain.

What is earned value in simple terms? ›

Earned value (EV) is an indicator that shows how much of your project's work is completed. The EV method compares completed tasks with planned tasks and their costs, giving you a clear measure of project performance. Simply put, it's a quick way to tell if you're behind schedule or over budget on your project.

What is the EVM rule? ›

In EVMs, the voter has to simply press the blue button on Ballot Unit against the candidate and symbol of his choice and the vote is recorded.

What are the core concepts of Earned Value Management? ›

Basic Concepts of Earned Value Management (EVM)- Part 1

Simply stated, EMV compares what you've received or produced to what you've spent. The EVM continuously monitors the percent complete of the project, the planned value (PV), earned value (EV), and actual costs (AC) expended to produce the work of the project.

What best defines earned value? ›

This method relies on a key measure known as the project's earned value. Oftentimes the term “earned value” is defined as the “budgeted cost of worked performed” or BCWP.

How is EVM calculated? ›

Earned value management formulas
Formula NameFormula
Schedule Performance IndexSPI = EV / PV
Estimate At CompletionEAC = BAC / CPI
Estimate To CompletionETC = EAC – AC
To-Complete Performance Index (BAC)TCPI = (BAC-EV) / (BAC-AC)
7 more rows

What is Earned Value Management in Agile? ›

Earned Value Management (EVM) is a good practice approach used for the planning, management and control of projects and programmes. It is a project management technique which measures cost and schedule against a baseline.

Top Articles
5 Sector ETFs That Beat the Market in Q4
ETFs with largest inflows underperform rivals, studies show
Nybe Business Id
Craigslist St. Paul
Fat Hog Prices Today
Pinellas County Jail Mugshots 2023
Celebrity Extra
Blanchard St Denis Funeral Home Obituaries
Boomerang Media Group: Quality Media Solutions
Wellcare Dual Align 129 (HMO D-SNP) - Hearing Aid Benefits | FreeHearingTest.org
Unitedhealthcare Hwp
Devotion Showtimes Near Mjr Universal Grand Cinema 16
Sissy Hypno Gif
سریال رویای شیرین جوانی قسمت 338
David Packouz Girlfriend
41 annonces BMW Z3 occasion - ParuVendu.fr
City Of Spokane Code Enforcement
Weather In Moon Township 10 Days
Help with Choosing Parts
VMware’s Partner Connect Program: an evolution of opportunities
Bend Pets Craigslist
Gem City Surgeons Miami Valley South
Razor Edge Gotti Pitbull Price
Ess.compass Associate Login
iZurvive DayZ & ARMA Map
Craigslist In Visalia California
Ups Print Store Near Me
Brbl Barber Shop
Teekay Vop
Finding Safety Data Sheets
Villano Antillano Desnuda
Lindy Kendra Scott Obituary
Uno Fall 2023 Calendar
Stubhub Elton John Dodger Stadium
Stolen Touches Neva Altaj Read Online Free
In Branch Chase Atm Near Me
Metra Union Pacific West Schedule
Craigslist In Myrtle Beach
Samsung 9C8
How to Destroy Rule 34
Montrose Colorado Sheriff's Department
Thanksgiving Point Luminaria Promo Code
Craigslist Ludington Michigan
Miracle Shoes Ff6
Chathuram Movie Download
18006548818
boston furniture "patio" - craigslist
Zits Comic Arcamax
Charlotte North Carolina Craigslist Pets
Southwind Village, Southend Village, Southwood Village, Supervision Of Alcohol Sales In Church And Village Halls
Texas Lottery Daily 4 Winning Numbers
Latest Posts
Article information

Author: Margart Wisoky

Last Updated:

Views: 6154

Rating: 4.8 / 5 (58 voted)

Reviews: 81% of readers found this page helpful

Author information

Name: Margart Wisoky

Birthday: 1993-05-13

Address: 2113 Abernathy Knoll, New Tamerafurt, CT 66893-2169

Phone: +25815234346805

Job: Central Developer

Hobby: Machining, Pottery, Rafting, Cosplaying, Jogging, Taekwondo, Scouting

Introduction: My name is Margart Wisoky, I am a gorgeous, shiny, successful, beautiful, adventurous, excited, pleasant person who loves writing and wants to share my knowledge and understanding with you.